1. Large scaleEquipment relocationSpecifically, conduct specific investigations into the loading and unloading standards along the routes and on both sides, understand the status of transport routes, draft transportation methods, clearly specify safety assurance measures, and formulate transportation countermeasures.
2. Before relocating large equipment, the roadbed works should be moved downward. Conduct on-site investigations and take measures to avoid tilting during loading and unloading. to overturn; Regarding the highway bridges along the route, Tunnels. Sections and other surfaces should be inspected and checked regularly, and reinforcement should be carried out when necessary.
3. The slope of the transport road for large machinery and equipment must not exceed 15°; If compliance with regulations is not possible, try to consult the manufacturer for approval and formulate safe and reliable safety assurance measures.
4. If there are power lines on the transport road, maintain a distance when using them; otherwise, try to use protective measures.
5. When transporting large equipment by cart, stability calculations should be conducted and measures to avoid obvious damage or vibration should be selected. Before proceeding, the horn should be sounded first. When carrying a passenger, the speed must not exceed 5km/h–10km/h. When driving safely, a road clearing vehicle and escort liaison person should be provided.
6. Remove the large parts from the carEquipment relocationWhen loading and unloading trucks, service channels should be consolidated and require sufficient spacing and length. After loading, the service channel must not have uneven downward movement.
7. When establishing loading and unloading service channels, the distortion caused by the yellow bounce and the hull floating during loading should be taken into account.
8. When using two different tow belts at different speeds for loading and unloading industrial equipment, measures should be taken to ensure even force distribution and the traction belt speed is consistent. The force point of the traction belt should be below the center of gravity of the machine.
9. The center of gravity of the other half to be dragged should be placed at the critical position of the pad. When transporting the ring-shaped other half, wooden pillow wedges should be placed on top; For tall, large objects with a small base area, measures to avoid tilting should be chosen; For thick-walled pipes or easily bent objects, engineering reinforcement measures should be selected.
10. The cable ropes used for transporting pulley sets must be accounted for and inspected every few days during use. It is prohibited to tie or haul pulley assemblies on unreinforced buildings or operating equipment. When driving piles and tying the basic foundation pulley group for transporting pulley sets, the condition of underground machinery and equipment should be understood and their bearing capacity calculated.
11. In risk areas where the main galvanized steel wire is worn and the inside of the main movable pulley assembly is prohibited, operators are prohibited from staying or staying.
12. If the center is suspended during the relocation of large equipment, measures should be taken to prevent the other half from rotating. At night, a green light should be set up for public notice, and staff should be assigned to supervise the area.