Many projects rely on crane equipment during implementation, so lifting equipment needs to be installed. Now, let me briefly introduce the craneEquipment installationThings to pay attention to at the time.
1. According to the packing list for single-girder crane equipment, inspect the models, specifications, and quantities of equipment, documentation, and accessories, ensuring they meet the requirements of planning and equipment technical documents, and must have factory certificates of conformity and necessary factory test records.
2. Mechanical and electrical equipment should be free of deformation, damage, or corrosion; wire ropes should not be corroded, damaged, bent, coiled, twisted, cracked, or loose.
3. Equipment and technical documentation should be complete.
4. The coordinate position, elevation, span, and surface flatness of the hanging rails should meet planning and installation requirements.
5. Before lifting, the electric single-girder suspension crane should be re-inspected according to the table below. After being installed on the track, the gap between the inner side of the wheel flange and the I-beam rail edge should be 3~5 millimeters.
The above is an introduction to the crane provided by the editorEquipment installationHope this is helpful to you.