Dust removalEquipment installationSubsequent adjustment steps.
After the dust removal equipment is installed, conduct a joint trial run. All equipment in the operating system runs continuously for 24 hours. Check whether the inlet and outlet air volume, pressure, turbidity, and other parameters comply with planning rules. Check whether the differential pressure system is functioning properly and whether the system interlocks are functioning properly, and perform corresponding calculations.
The steps for commissioning the dust collector are as follows:
1. Lubrication system inspection: Check whether the lubrication system is operating normally, whether the grease at each lubrication point is sufficient, and whether the deceleration is sufficient.
2. Blowing system commissioning: Check whether the blowing pipe and valve are installed correctly, whether the cylinder block operates smoothly, and whether the pulse valve is operated correctly. Operate the air blowing system to check whether the operation sequence of the pulse valve and valves is correct, whether the air pressure meets the planned rules, and whether the valve is properly sealed.
3. Dust removal system commissioning: Check whether the operation of the dust removal valve is correct and convenient, whether the plate chain conveyor and bucket elevator are stable and secure, and whether the backstop is loose. Click to check whether the rotation direction of the plate chain conveyor and bucket elevator is correct. The operating system runs continuously for 12 hours, and check whether the motor's operating current and current are normal; Check for abnormal noise during operation; Check whether the fan and motor bearing temperatures are normal, and so on.